| Dimension | Rating | Basis |
|---|---|---|
| Schedule performance | RED | SPI 0.86: earned value SAR 91,075 against planned value SAR 105,410, schedule variance −SAR 14,335; physical progress 37.17% against 43.02% planned, −5.85 points. The movement of the week is the tanks assembly (9.2), reported at 25% against the 38.10% the baseline calls for: −13.10 points on the activity, −5.88 points on the project. The +4.22 points earned in the week were overtaken by 12.83 points of planned progress. |
| Completion date | AMBER | The schedule still forecasts 26 Nov 2026, the baseline date, but 9.2 has 13 working days to 15 November for the last 75% of a 44.90% package. At the 2.00 points a working day earned in its first two weeks, the remaining 75% needs 38 more working days: the assembly would finish about 14 December, four weeks after its date, and the chain behind it moves with it. |
| Cost performance | AMBER | CPI 1.30 on the SAR 70,000 of cost recorded (CV +SAR 21,075, EAC SAR 188,306). Earned value passed the recorded cost only because the SAR 110,000 tanks package is 25% delivered with no cost posted: the index is not yet a true cost position and EAC is provisional. |
| Critical path | AMBER | 9 of the 15 open activities carry zero total float and 68.2% of the weighted value of the works sits in the activities that drive the 15 to 26 November window; the tanks assembly alone is 44.90% of it. |
| Data quality | AMBER | The summary cell of the schedule reads 37.44% while its own activity lines add to 37.17%: 10.2 was revised from 40% to 30% and the total still carries the old figure. The actual cost column repeats the activity budget, 9.1 is still 75% with its finish of 21 October passed, and actual starts are recorded ahead of the baseline on 9.1 (10 Oct), 9.2 (18 Oct) and 10.2 (20 Oct). |
| Checkpoint | What it measures | Planned | Actual | Variance |
|---|---|---|---|---|
| 24 Feb 2026 | Engineering drawings complete (7.1, 7.2, 7.3) | 6.12% | 6.12% | 0.00 pts |
| 30 Jun 2026 | Civil and structural works complete (8.1, 8.2) | 22.86% | 22.86% | 0.00 pts |
| 17 Oct 2026 | First weekly update — position as reported | 24.69% | 25.80% | +1.10 pts |
| 24 Oct 2026 | Weekly update of 24 October 2026 — position as reported | 30.19% | 32.95% | +2.75 pts |
| 31 Oct 2026 | Data date — weighted progress reported now | 43.02% | 37.17% | −5.85 pts |
| Cost variance (CV = EV − AC) | +SAR 21,075 |
| Schedule variance (SV = EV − PV) | −SAR 14,335 |
| Cost performance index (CPI) | 1.30 |
| Schedule performance index (SPI) | 0.86 |
| Estimate at completion (EAC = BAC ÷ CPI) | SAR 188,306 |
| Variance at completion (VAC = BAC − EAC) | +SAR 56,694 |
| Budget spent to date (AC ÷ BAC) | 28.57% |
| WBS | Workstream | Weight | PV | EV | AC | CV | CPI |
|---|---|---|---|---|---|---|---|
| 7 | Engineering Drawings | 6.12% | 15,000 | 15,000 | 15,000 | 0 | 1.00 |
| 8 | Civil & Structural Works | 16.73% | 41,000 | 41,000 | 41,000 | 0 | 1.00 |
| 9 | Tanks Errection | 53.27% | 49,410 | 33,125 | 7,500 | 25,625 | 4.42 |
| 10 | Mechanical Works | 13.06% | 0 | 1,950 | 6,500 | −4,550 | 0.30 |
| 11 | Electrical & Control Panels | 8.37% | 0 | 0 | 0 | 0 | n/a |
| 12 | Testing & Commissioning | 2.45% | 0 | 0 | 0 | 0 | n/a |
| – | Total | 100.00% | 105,410 | 91,075 | 70,000 | 21,075 | 1.30 |
| WBS | Workstream | Weight | Planned / actual complete | Planned | Actual | Variance | Status | Activities |
|---|---|---|---|---|---|---|---|---|
| 7 | Engineering Drawings | 6.12% | 100.00% | 100.00% | +0.00 pts | Completed | 3 | |
| 8 | Civil & Structural Works | 16.73% | 100.00% | 100.00% | +0.00 pts | Completed | 2 | |
| 9 | Tanks Errection | 53.27% | 37.86% | 25.38% | −12.48 pts | In Progress | 6 | |
| 10 | Mechanical Works | 13.06% | 0.00% | 6.09% | +6.09 pts | In Progress | 3 | |
| 11 | Electrical & Control Panels | 8.37% | 0.00% | 0.00% | +0.00 pts | Planned | 4 | |
| 12 | Testing & Commissioning | 2.45% | 0.00% | 0.00% | +0.00 pts | Planned | 2 | |
| – | Total | 100.00% | 43.02% | 37.17% | −5.85 pts | 20 |
| # | Milestone | Contract date | Status | Workstream forecast finish | Variance (working days) |
|---|---|---|---|---|---|
| M1 | Engineering Drawings | 08 Mar 2026 | Achieved | 24 Feb 2026 (actual) | −10 |
| M2 | Civil & Structural Works | 30 Jun 2026 | Achieved | 30 Jun 2026 (actual) | 0 |
| M3 | Tanks Errection | 17 Nov 2026 | In progress | 19 Nov 2026 | +2 |
| M4 | Mechanical Installation | 21 Nov 2026 | In progress | 23 Nov 2026 | +2 |
| M5 | Electrical Installation | 18 Nov 2026 | Planned | 19 Nov 2026 | +1 |
| M6 | Testing & Commissioning | 24 Nov 2026 | Planned | 26 Nov 2026 | +2 |
| WBS | Workstream | Weight | Baseline finish | Forecast finish | Var. wd |
|---|---|---|---|---|---|
| 7 | Engineering Drawings | 6.12% | 24 Feb 2026 | 23 Feb 2026 | −1 |
| 8 | Civil & Structural Works | 16.73% | 30 Jun 2026 | 30 Jun 2026 | 0 |
| 9 | Tanks Errection | 53.27% | 19 Nov 2026 | 19 Nov 2026 | 0 |
| 10 | Mechanical Works | 13.06% | 23 Nov 2026 | 23 Nov 2026 | 0 |
| 11 | Electrical & Control Panels | 8.37% | 21 Nov 2026 | 21 Nov 2026 | 0 |
| 12 | Testing & Commissioning | 2.45% | 26 Nov 2026 | 26 Nov 2026 | 0 |
| WBS | Activity | Status | Weight % | Planned % | Current % | Variance pts | Last week % | Weekly gain | Actual start | Actual end | Forecast finish | Responsible | Comment / evidence |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 7.1 | Civil Drawings | Completed | 2.04 | 100.0% | 100% | 0.00 | 100% | 0 | 15 Feb 2026 | 22 Feb 2026 | 22 Feb 2026 | — | — |
| 7.2 | Mechanical Drawings | Completed | 2.04 | 100.0% | 100% | 0.00 | 100% | 0 | 15 Feb 2026 | 21 Feb 2026 | 21 Feb 2026 | — | — |
| 7.3 | Electrical Drawings | Completed | 2.04 | 100.0% | 100% | 0.00 | 100% | 0 | 17 Feb 2026 | 24 Feb 2026 | 24 Feb 2026 | — | — |
| 8.1 | Tanks & Pump Slab Foundation | Completed | 14.29 | 100.0% | 100% | 0.00 | 100% | 0 | 14 Jun 2026 | 29 Jun 2026 | 29 Jun 2026 | — | — |
| 8.2 | Pipe Supports | Completed | 2.45 | 100.0% | 100% | 0.00 | 100% | 0 | 20 Jun 2026 | 30 Jun 2026 | 30 Jun 2026 | — | — |
| 9.1 | Steel Beam Foundation | In Progress | 3.06 | 100.0% | 75% | −25.00 | 75% | 0 | 10 Oct 2026 | — | 21 Oct 2026 | — | — |
| 9.2 | Tanks Assembly | In Progress | 44.90 | 38.1% | 25% | −13.10 | 15% | +10 | 18 Oct 2026 | — | 15 Nov 2026 | — | — |
| 9.3 | Ladder, Vent, SS Supports | Not Started | 0.82 | 0.0% | 0% | 0.00 | 0% | 0 | — | — | 16 Nov 2026 | — | — |
| 9.4 | Mechanical Level Indicator | Not Started | 1.63 | 0.0% | 0% | 0.00 | 0% | 0 | — | — | 16 Nov 2026 | — | — |
| 9.5 | Overall Finishing | Not Started | 0.41 | 0.0% | 0% | 0.00 | 0% | 0 | — | — | 17 Nov 2026 | — | — |
| 9.6 | Testing (tanks) | Not Started | 2.45 | 0.0% | 0% | 0.00 | 0% | 0 | — | — | 19 Nov 2026 | — | — |
| 10.1 | Pumps Installation | Not Started | 10.20 | 0.0% | 0% | 0.00 | 0% | 0 | — | — | 17 Nov 2026 | — | — |
| 10.2 | Pipes & Fittings Installation | In Progress | 2.65 | 0.0% | 30% | +30.00 | 40% | −10 | 20 Oct 2026 | — | 22 Nov 2026 | — | — |
| 10.3 | Testing – Hydrotest | Not Started | 0.20 | 0.0% | 0% | 0.00 | 0% | 0 | — | — | 23 Nov 2026 | — | — |
| 11.1 | Electrical Cables, Switches, Trays, Conduits | Not Started | 2.65 | 0.0% | 0% | 0.00 | 0% | 0 | — | — | 21 Nov 2026 | — | — |
| 11.2 | Level Control Panel Installation | Not Started | 2.45 | 0.0% | 0% | 0.00 | 0% | 0 | — | — | 17 Nov 2026 | — | — |
| 11.3 | Pump Control Panel Installation | Not Started | 3.06 | 0.0% | 0% | 0.00 | 0% | 0 | — | — | 18 Nov 2026 | — | — |
| 11.4 | Testing (electrical) | Not Started | 0.20 | 0.0% | 0% | 0.00 | 0% | 0 | — | — | 19 Nov 2026 | — | — |
| 12.1 | Function & Operation Test | Not Started | 0.41 | 0.0% | 0% | 0.00 | 0% | 0 | — | — | 25 Nov 2026 | — | — |
| 12.2 | Documentation & As Built Drawings | Not Started | 2.04 | 0.0% | 0% | 0.00 | 0% | 0 | — | — | 26 Nov 2026 | — | — |
| – | Total — 20 activities | 100.00 | 43.02% | 37.17% | −5.85 | ||||||||
| WBS | Activity | Window | Target % by 7 Nov | Manpower / material readiness | Action needed | Owner |
|---|---|---|---|---|---|---|
| 9.1 | Steel Beam Foundation | Close-out · by 7 Nov | 100.0% | Requirement: the remaining 25% confirmed with its evidence | Sign the activity off and release the crew to the tanks; its finish of 21 Oct has passed. | — |
| 9.2 | Tanks Assembly | Recovery · from 31 Oct | 72.0% | Requirement: a second erection crew or a second shift through November (decide) | 38.10% was the plan for 31 Oct. The dates now on the schedule call for 72% by 7 Nov (66.7% on the baseline): 5.77 points a working day are needed to 15 Nov against 2.00 earned. | — |
| 10.2 | Pipes & Fittings Installation | Control action · by 7 Nov | 0.0% | Revision of the 24 Oct figure (40%) to be explained | Confirm the position and the re-link to 10.1 and 10.3, or park the early work. | — |
| WBS | Activity | Required by | Type | Requirement | Weight | Readiness |
|---|---|---|---|---|---|---|
| 9.2 | Tanks Assembly | 22 Oct | Material, subcontractor, equipment | Tank plates and structural steel; erection crew; crane and lifting access | 44.90% | — |
| 10.1 | Pumps Installation | 16 Nov | Material, equipment, access | Pumps and pipe spools on site; lifting and rigging; access to the pump room | 10.20% | — |
| 11.3 | Pump Control Panel Installation | 18 Nov | Material, approval | Control panel delivered; panel shop drawings approved | 3.06% | — |
| 11.1 | Electrical Cables, Switches, Trays, Conduits | 18 Nov | Material | Cables, trays, conduits and switches on site | 2.65% | — |
| 11.2 | Level Control Panel Installation | 16 Nov | Material, approval | Level panel delivered; electrical shop drawings approved | 2.45% | — |
| 9.6 | Testing (tanks) | 18 Nov | Client coordination, access | Access to tank internals; client witness for the test | 2.45% | — |
| 9.4 | Mechanical Level Indicator | 16 Nov | Material | Level indicator delivered | 1.63% | — |
| 9.3 | Ladder, Vent, SS Supports | 16 Nov | Material | Ladders, vents and stainless supports delivered | 0.82% | — |
| 12.1 | Function & Operation Test | 24 Nov | Client coordination | Client attendance; test packs issued | 0.41% | — |
| Blocker | Affected activity | Schedule impact | Action required | Responsible | Due date | Status |
|---|---|---|---|---|---|---|
| Tanks assembly at 25% against 38.10% planned | 9.2 → 9.3, 9.4, 10.1, 11.2 | −13.10 points on the activity, −5.88 on the project, 13 working days to 15 Nov | Add a second erection crew or shift; agree the recovery with PDC and AECOM | — | 7 Nov 2026 | Open |
| Steel beam foundation at 75% with its finish of 21 Oct passed | 9.1 → 9.2 | 3 days of exposure on the feeder to 44.90% of the weight | Close the last 25% and sign 9.1 off | — | 7 Nov 2026 | Open |
| Pipes & fittings revised from 40% to 30% without a note | 10.2 → 10.1, 10.3 | −0.27 points this week and an unexplained correction in the record | Record the reason and re-link 10.1, 10.2 and 10.3 | — | 7 Nov 2026 | Open |
| No cost posted on the SAR 110,000 tanks package | 9 | CPI 1.30 and EAC SAR 188,306 rest on SAR 70,000 of recorded cost only | Code and post the steel and tank invoices | — | 7 Nov 2026 | Open |
| Four contractual milestones forecast +1 or +2 working days | M3–M6 | 19, 19, 23 and 26 November against contract dates of 17, 18, 21 and 24 November | Take the days out inside the tanks and pumps windows before 15 Nov | — | 14 Nov 2026 | Open |
| No schedule buffer: 9 of the 15 open activities at zero total float | All | 68.2% of the weighted works sit on the driving chain | Freeze the 16 to 18 Nov material and access commitments | — | 16 Nov 2026 | Monitor |
| WBS | Activity | Status | Weight % | % comp. | Est. cost | Actual cost | EV | Baseline start | Baseline finish | Current start | Current finish | Var. wd | Total float | Free float | Predecessors | Successors |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 7.1 | Civil Drawings | Completed | 2.04 | 100 | 5,000 | 5,000 | 5,000 | 15 Feb 2026 | 19 Feb 2026 | 15 Feb 2026 | 22 Feb 2026 | +2 | – | – | – | – |
| 7.2 | Mechanical Drawings | Completed | 2.04 | 100 | 5,000 | 5,000 | 5,000 | 15 Feb 2026 | 21 Feb 2026 | 15 Feb 2026 | 21 Feb 2026 | 0 | – | – | – | – |
| 7.3 | Electrical Drawings | Completed | 2.04 | 100 | 5,000 | 5,000 | 5,000 | 17 Feb 2026 | 24 Feb 2026 | 17 Feb 2026 | 23 Feb 2026 | −1 | – | – | – | – |
| 8.1 | Tanks & Pump Slab Foundation | Completed | 14.29 | 100 | 35,000 | 35,000 | 35,000 | 14 Jun 2026 | 27 Jun 2026 | 14 Jun 2026 | 27 Jun 2026 | 0 | – | – | – | – |
| 8.2 | Pipe Supports | Completed | 2.45 | 100 | 6,000 | 6,000 | 6,000 | 20 Jun 2026 | 30 Jun 2026 | 20 Jun 2026 | 30 Jun 2026 | 0 | – | – | – | – |
| 9.1 | Steel Beam Foundation | In Progress | 3.06 | 75 | 7,500 | 7,500 | 5,625 | 14 Oct 2026 | 19 Oct 2026 | 14 Oct 2026 | 21 Oct 2026 | +2 | 0 | 0 | – | 9.2 FS |
| 9.2 | Tanks Assembly | In Progress | 44.90 | 25 | 110,000 | – | 27,500 | 22 Oct 2026 | 15 Nov 2026 | 18 Oct 2026 | 15 Nov 2026 | 0 | 0 | 0 | 9.1 FS | 9.3, 9.4, 10.1, 11.2 |
| 9.3 | Ladder, Vent, SS Supports | Not Started | 0.82 | 0 | 2,000 | – | – | 16 Nov 2026 | 16 Nov 2026 | 16 Nov 2026 | 16 Nov 2026 | 0 | 9 | 9 | 9.2 FS | – |
| 9.4 | Mechanical Level Indicator | Not Started | 1.63 | 0 | 4,000 | – | – | 16 Nov 2026 | 16 Nov 2026 | 16 Nov 2026 | 16 Nov 2026 | 0 | 0 | 0 | 9.2 FS | 9.5 |
| 9.5 | Overall Finishing | Not Started | 0.41 | 0 | 1,000 | – | – | 17 Nov 2026 | 17 Nov 2026 | 17 Nov 2026 | 17 Nov 2026 | 0 | 0 | 0 | 9.4 FS | 9.6 |
| 9.6 | Testing (tanks) | Not Started | 2.45 | 0 | 6,000 | – | – | 18 Nov 2026 | 19 Nov 2026 | 18 Nov 2026 | 19 Nov 2026 | 0 | 3 | 3 | 9.5 FS | 12.1 |
| 10.1 | Pumps Installation | Not Started | 10.20 | 0 | 25,000 | – | – | 16 Nov 2026 | 17 Nov 2026 | 16 Nov 2026 | 17 Nov 2026 | 0 | 0 | 0 | 9.2 FS | 10.2, 11.1, 11.3 |
| 10.2 | Pipes & Fittings Installation | In Progress | 2.65 | 30 | 6,500 | 6,500 | 1,950 | 18 Nov 2026 | 22 Nov 2026 | 20 Oct 2026 | 22 Nov 2026 | 0 | 0 | 0 | 10.1 FS | 10.3 |
| 10.3 | Testing – Hydrotest | Not Started | 0.20 | 0 | 500 | – | – | 23 Nov 2026 | 23 Nov 2026 | 23 Nov 2026 | 23 Nov 2026 | 0 | 0 | 0 | 10.2 FS | 12.1 |
| 11.1 | Electrical Cables, Switches, Trays, Conduits | Not Started | 2.65 | 0 | 6,500 | – | – | 18 Nov 2026 | 21 Nov 2026 | 18 Nov 2026 | 21 Nov 2026 | 0 | 5 | 5 | 10.1 FS | – |
| 11.2 | Level Control Panel Installation | Not Started | 2.45 | 0 | 6,000 | – | – | 16 Nov 2026 | 17 Nov 2026 | 16 Nov 2026 | 17 Nov 2026 | 0 | 1 | 1 | 9.2 FS | 11.4 |
| 11.3 | Pump Control Panel Installation | Not Started | 3.06 | 0 | 7,500 | – | – | 18 Nov 2026 | 18 Nov 2026 | 18 Nov 2026 | 18 Nov 2026 | 0 | 0 | 0 | 10.1 FS | 11.4 |
| 11.4 | Testing (electrical) | Not Started | 0.20 | 0 | 500 | – | – | 19 Nov 2026 | 19 Nov 2026 | 19 Nov 2026 | 19 Nov 2026 | 0 | 3 | 3 | 11.3 FS, 11.2 FS | 12.1 |
| 12.1 | Function & Operation Test | Not Started | 0.41 | 0 | 1,000 | – | – | 24 Nov 2026 | 25 Nov 2026 | 24 Nov 2026 | 25 Nov 2026 | 0 | 1 | 0 | 9.6 FS, 10.3 FS, 11.4 FS | 12.2 |
| 12.2 | Documentation & As Built Drawings | Not Started | 2.04 | 0 | 5,000 | – | – | 24 Nov 2026 | 26 Nov 2026 | 24 Nov 2026 | 26 Nov 2026 | 0 | 0 | 0 | 12.1 SS | – |
| – | Total — 20 activities | 100.00 | 37.17 | 245,000 | 70,000 | 91,075 | ||||||||||