Tank 1 and tank 2: floor sheets closed, jointing and sealing of the wall panels, torque check and fixation. Weighted progress at this date 37.17% against 43.02% planned. Open the report · Timeline of updates














Tanks assembly: floor sheets laid, sealed and inspected in the first week of erection. Weighted progress at this date 32.95%. Open the 24 October report · Timeline of updates









Steel skid erected, joints welded, cold galvanizing applied in three layers. Weighted progress at that date 25.80%. Open the 17 October report · Timeline of updates